C Transmission Line Project Update

November 2025

Map showing Copper Cove with a C-Tank Booster Pump Station, Transmission Line, and marked sites like Little John Rd and Saddle Creek Golf Club.

Activity is ramping up at Copper Cove. Mozingo Construction is preparing to begin mainline installation, with a small crew already mobilizing at Tank C this November with crews beginning with the potholing procces during the week of 17th. Full pipeline installation is scheduled to begin in December.

Important Notice:

Changeable Message Signs will be placed during the week of November 17th along Little John Road to notify drivers of upcoming road closures.

Preliminary Road Closure Schedule

  • Dec 8 – Dec 19, 2025: From Kiva Pl. to Moccasin St.
  • Dec 22, 2025 – Jan 8, 2026: From Moccasin to Flint Trail
  • Jan 9 – Jan 26, 2026: From Flint Trail to south Bow Dr.
  • Jan 27 – Feb 2, 2026: From south Bow Dr. to Saddle Creek
  • Feb 3 – Feb 10, 2026: From Saddle Creek to north Bow Dr.
  • Feb 26 – Mar 4, 2026: From Quail Hill Rd. to Arrowhead St.
  • Mar 5 – Mar 13, 2026: From Arrowhead St. to CCWD Tank Site

Dates are subject to change due to weather and production.