C Transmission Line Project Update
November 2025

Activity is ramping up at Copper Cove. Mozingo Construction is preparing to begin mainline installation, with a small crew already mobilizing at Tank C this November with crews beginning with the potholing procces during the week of 17th. Full pipeline installation is scheduled to begin in December.
Important Notice:
Changeable Message Signs will be placed during the week of November 17th along Little John Road to notify drivers of upcoming road closures.
Preliminary Road Closure Schedule
- Dec 8 – Dec 19, 2025: From Kiva Pl. to Moccasin St.
- Dec 22, 2025 – Jan 8, 2026: From Moccasin to Flint Trail
- Jan 9 – Jan 26, 2026: From Flint Trail to south Bow Dr.
- Jan 27 – Feb 2, 2026: From south Bow Dr. to Saddle Creek
- Feb 3 – Feb 10, 2026: From Saddle Creek to north Bow Dr.
- Feb 26 – Mar 4, 2026: From Quail Hill Rd. to Arrowhead St.
- Mar 5 – Mar 13, 2026: From Arrowhead St. to CCWD Tank Site
Dates are subject to change due to weather and production.